Our team partnered with the client to deliver site remediation works at a coal site in NSW. The scope involved remediating over 7,000m³ of asbestos-contaminated materials and residual demolition waste, including excavation, transportation, placement and capping. An additional 32,000 m3 of earthworks and civil construction was undertaken to stabilise the site’s steeply undulating terrain for future use.
To support the safe and efficient delivery of the project, a detailed remediation plan was developed in collaboration with Kleinfelder and the bulk earthworks civil design team prior to construction.
During the works, the team identified and segregated suitable site-won clay soils for use as capping material, while also constructing a sediment basin and rip rap stormwater bypass channel to effectively manage site runoff. All activities were carried out in accordance with the site’s Environment Protection License.
Following remediation, final surfaces were treated with a compost blanket to promote revegetation, restoring natural ground cover and providing long-term site stability.
Given the close proximity of neighbouring residents and schools, dust management remained a critical focus throughout the project. Measures included the installation of a permanent onsite water cart fill stand and a staged validation approach, which allowed completed areas to be progressively sealed with the compost blanket growth medium, minimising exposure and supporting immediate stabilisation.
Summary
- Placed 7,650m3 of unsuitable materials in the capped area
- Additional fill of 32,000m3 to recontour the site
- Validation of the site was conducted in a staged approach
- Concentrated management of dust on the site