After the completion of our design and construction of the Linewide Marrickville ground water treatment plant, our team continued the support with operations and maintenance.
Summary of the services delivered:
- Remote monitoring support including weekends and public holidays
- Process optimisation and engineering support 24/7
- 129 days of operator on site
- Solid waste classification and disposal
- Field operations and maintenance
- Spare part procurement
- Treated water conformance analysis and reviews
- Filter media changeovers and disposal
- Scheduled servicing of mechanical and electrical components
- Supply of chemicals
- Demobilisation
cLIENT
Systems Connect Line-Wide
tIMEFRAME
12 months
lOCATION
NSW